REINFORCED BARS TO RETAINING WALL
FIXING REINFORCED BARS TO RETAINING WALL
BASEMENT REINFORCED BARS TO RETAINING WALL
BASEMENT REINFORCED BARS TO RETAINING WALL
PAD FOOTING AND STARTER BARS
CASTING OF PAD FOOTING
EARTH FILLING TO GROUND LEVEL 
MASONRY WORKS ON FOUNDATION WALL
MASONRY WORKS ON FOUNDATION WALL
BACK FILLING TO GROUND FLOOR LEVEL
BACK FILLING TO GROUND FLOOR LEVEL
BACK FILLING TO GROUND FLOOR LEVEL
SUPERVISING EARTH WORK (SITE ENGINEER)
MASONRY WORK TO THE FOUNDATION WALL
MASONRY WORK TO THE FOUNDATION WALL
REMOVING FORMWORK TO BASEMENT COLUMNS
CONSTRUCTION TEAM (CLIENT, CONSULTANTS  AND CONTRACTOR) INSPECTING SITE BEFORE SITE MEETING
CONSTRUCTION TEAM (CLIENT, CONSULTANTS  AND CONTRACTOR) INSPECTING SITE BEFORE SITE MEETING
FIXING REINFORCEMENTS TO THE INTERMEDIATE BEAMS
MASONRY WORK CONTINUES
COLUMNS AT THE BASEMENT SIDE
COLUMNS AND RETAINING WALL AT THE BASEMENT SIDE
COMPACTION OF THE IMPORTED FILL TO MAKEUP LEVEL
COMPACTION OF THE IMPORTED FILL TO MAKEUP LEVEL
COMPACTION OF THE IMPORTED FILL TO MAKEUP LEVEL
BLOCK WORK TO THE BASEMENT WALLS
IMPORTING FILL MATERIAL
COMPACTION OF IMPORTED FILL
FIXING FORMWORK FOR BASEMENT SLAB
HARDCORE FILLING
CONSTRUCTION TEAM INSPECTING THE WORK
CONSTRUCTION TEAM INSPECTING THE WORK
CONSTRUCTION TEAM INSPECTING THE WORK