- BUILDING PROCESS OF ECO SHELLS & MONOLITHIC DOMES -
____________________________________________________________________
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/ed7a8668931785.5b6ef42ef1bac.jpg)
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/986bda68931785.5b6ef42ef155d.jpg)
Step 1. "FORMING STAKES" FOR AIRFORM Step 2. FORMING BOARDS INSIDE STAKES
____________________________________________________________________
![architecture dome](https://mir-s3-cdn-cf.behance.net/project_modules/1400/09de9868931785.5b6ef42fe8a88.jpg)
Step 3. PLUMBING + ELECTRICAL
____________________________________________________________________
![architecture dome](https://mir-s3-cdn-cf.behance.net/project_modules/1400/f3fd2468931785.5b6ef42fe8547.jpg)
Step 4. REBAR CROSS PATTERN WITH CONCRETE POURED ON TOP + REBAR ON END.
____________________________________________________________________
- ECO SHELL -
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/ebe28b68931785.5b6f0750dd707.jpg)
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/e035fb68931785.5b6f0750ddc3e.jpg)
Step 5. "AIRFORM" IS PLACED UNDERNEATH Step 6. CONCRETE IS APPLIED BY HAND OR WITH
CLAMP ANGLES. SHOTCRETE PUMP. 24 HOURS TO DRY.
____________________________________________________________________
- MONOLITHIC DOME -
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/9c19e368931785.5b6f26cd010f3.jpg)
![](https://mir-s3-cdn-cf.behance.net/project_modules/1400/fa3ea768931785.5b6f26cd00b75.jpg)
Step 5. "AIRFORM" IS PLACED ON THE RING Step 6. SHOTCRETE IS APPLIED TO
BASE AND IT IS INFLATED. THE INTERIOR SURFACE OF THE DOME.
____________________________________________________________________
![architecture dome](https://mir-s3-cdn-cf.behance.net/project_modules/1400/5378c168931785.5b6ef42fe92d5.jpg)
Step 7. INTERIOR PLASTER COATING IS APPLIED, THEN EXTERIOR IS COATED WITH ELASTOMERIC COATING
TO HELP WITH SOLAR REFLECTANCE + ANY LEAKS OR HAIRLINE CRACKS.
____________________________________________________________________
![](https://mir-s3-cdn-cf.behance.net/project_modules/disp/d46b0f68931785.5b6f410e982d1.gif)
![](https://mir-s3-cdn-cf.behance.net/project_modules/disp/d8480c68931785.5b6f410e98880.gif)
ECO SHELL MONOLITHIC DOME