Technical and Engineering Visualization

Engineering and Technical Illustrations and Animations
Live project
The clients, who are in Washington DC,came to us with the requirements of create an technical video for the Contractors in NY City , illustrating the process and clearly showing the sequence of steps.
The 8 steps are oultined in the requirements:
Step 1: Excavation Top-Heading and Flashcrete (Shotcrete 3”)
Step 2: Installing Wiremesh and Lattice Girder
Step 3: Applying Shotcrete Top Heading (1st Layer)
Step 4: Excavation Bench and Flashcrete (Shotcrete 3”)
Step 5: Installing Wiremesh and Lattice Girder
Step 6: Applying Shotcrete Bench (1st Layer)
Step 7: Applying Shotcrete Top Heading (2nd Layer)
Step 8: Applying Shotcrete Bench (2nd Layer)

The following imagery is from the project.

Technical and Engineering Visualization
Published:

Technical and Engineering Visualization

Illustration of Engineering Project. An Animation of the process for the Construction crew to follow: The clients, who are in Washington DC,came Read More

Published: