3 Level Basement. Project Execution

A Day on Meso Site 
Club Parramtta NSW, Australia

Series of photographs demonstrating groundwork process for 3 level basement installation by Meso Solutions. 

✔️ First things first - measuring and preparing site ground for the project. 
✔️ Pre-drilling starts after measuring to ensure smooth retaining wall installation.
✔️ Sheet piling follows after pre-drilling creating retaining walls around the project perimeter.
✔️ Site is ready for bulk excavations. 

As excavations continue further systems will have to be installed to successfully complete basement works:
✔️ Anchoring
✔️ Dewatering
✔️ MesoForm© Basement Walls
​​​​​​​ 
Measuring and preparing site ground for basement systems' installation.
Preparing Meso equipment for sheet pile installation. 
Sheet piles being driven into ground. It begins to look like a retaining wall. 
Company Background:

MESO Solutions is a nation-wide provider of in-ground works including:

▪️Design & Cert
▪️Sheet Piling
▪️Anchoring
▪️Dewatering
▪️Permanent Basement Walls


www.mesos.com.au
3 Level Basement. Project Execution
Published:

3 Level Basement. Project Execution

Published:

Creative Fields